Our Client: Michael Garron Hospital

Project Snapshot

Birnie Electric, in partnership with Maystar Construction, Gesco Mechanical and PBW High Voltage Ltd., supplied and installed two 1500kw diesel standby power generators complete with switchgear, remote radiators and load bank.

The installation replaced two existing 750kw diesel standby power generators in a project that had to be carefully planned and orchestrated to ensure the active hospital had a functioning backup power supply at all times. This was achieved through the use of two 1500kw temporary generators located on the outside of the building.

Construction Cost

Electrical: $6.3 million

Completed

Spring 2017

Contribution to Success

Our experienced team demonstrated an ability to complete this major undertaking while always keeping 100 percent redundant backup power to the hospital.

Client References

Michael Garron Hospital
Tony Martino
Office: 416-469-6580
E-mail: tonymartino@tegh.on.ca